Important Information


Re: Piling works on Westerman Homes, Field Farm development, llkeston Road, Stapleford.

We would like to take this opportunity to inform you that Piling works will commence at the above-mentioned site on Wednesday 6th February 2019.

We envisage that the piling works will take approximately five weeks to complete from commencement of works.

Piling works to front-line Plots No’s 80 – 87 will not commence before 9.30am each day.
The remaining plots behind the front-line plots will commence at 8.00am and finish at 5.00pm each day.

Every effort will be made to minimise any inconvenience from the forthcoming works. May we take this opportunity to thank you in advance for your patience and understanding.

We will have representatives on site throughout these works however should you have any questions or concerns please contact Paul Begley on 01159 389666.